Audit Reports

Audit reports display project account information and audit transactions.

You can generate the following Audit reports:

  • Change Management: Use this report to view project account information with log comments and change numbers. This report is grouped by change number.
  • Log: Use the Log report to view audit transactions containing the modified control account, work package or assignment, change number, and comment.
  • Project Planning Statistics: Use this report to view statistics about the project, including the mean and median duration and the values of control accounts and work packages. For work packages, the statistics are displayed by progress technique.
  • Work Authorization Document (WAD)/Control Account Information: Use this report to view the control account dates, budget information summarized by labor and other direct costs, and the notes entered in the control account.
  • Project Audit: Use this report to reconcile the values on the Budget tab of the Project Properties dialog box with those calculated by the Project Audit log. This report is an aggregated report, which supports selecting various criteria for the Sub-totals page of the Report Wizard.
  • Project Reconciliation: Use this report to reconcile the values on the Budget tab of the Project Properties dialog box with those calculated by the Project Audit log. This report supports filtering.